Prestige Evergreen Construction Timeline

Prestige Evergreen Construction Timeline: From Launch to Possession


Prestige Evergreen construction timeline from project launch to possession with key milestones

The construction timeline for Prestige Evergreen maps out the complete journey from launch to handover. The project will officially launch on 30 October 2025, and possession is scheduled for December 2029. Development will move in clear stages. It begins with earthwork and foundation, followed by the super-structure, interiors, and finishing. The last stage will cover landscaping and external works. This step-by-step plan ensures steady progress and on-time delivery, backed by Prestige Group’s trusted quality.

About the Project

Prestige Evergreen is part of the Prestige Raintree Park Township on Varthur Road, Whitefield. The project spans 28 acres within a 107-acre mixed-use community. It will offer 1–5 BHK apartments with sizes ranging from 650 sq. ft. to 3,698 sq. ft. In total, the development will deliver more than 2,000 homes supported by retail spaces, lifestyle amenities, and green landscapes.

Construction Timeline for Prestige Evergreen

Initial and Sub-Structure Work

  • Earthwork and leveling: November 2025 – March 2026
  • Foundation footing: February 2026 – June 2026
  • Plinth level and retaining walls: April 2026 – September 2026
  • Basement and parking structure: May 2026 – December 2026

Super-Structure Development

  • RCC/MS framed structure (towers): July 2026 – September 2027
  • Masonry construction (walls and partitions): October 2026 – March 2028
  • Plastering inside and outside: December 2026 – May 2028
  • Joinery (doors, windows, ventilators): March 2027 – December 2028
  • Basic electrification, sanitary, and water supply: April 2027 – January 2029
  • Flooring, tiles, and dadoing: July 2027 – February 2029
  • Railing and grill fixing: August 2027 – February 2029

Finishing Works

  • Electrification and sanitary finishing: January 2028 – August 2029
  • Painting and interiors: March 2028 – October 2029
  • Fire safety fittings and systems: March 2028 – September 2029
  • Weatherproofing and elevation works: April 2028 – October 2029
  • Landscaping and external works: August 2029 – November 2029

Key Milestones for Prestige Evergreen

  • Project Launch: 30 October 2025
  • Super-Structure Completion: September 2027
  • Interior Finishing & External Works: 2028 – 2029
  • Possession: December 2029

Conclusion

The Prestige Evergreen construction timeline provides a clear roadmap from launch to possession. Work will start with foundation activities in late 2025. Towers will rise through 2026 and 2027. Interior and finishing works will be completed between 2028 and 2029.

By December 2029, Prestige Evergreen will be ready for residents. The project will deliver spacious apartments, premium amenities, landscaped gardens, and retail spaces as part of a modern township. With its structured timeline and Prestige Group’s trusted legacy, it is set to become one of East Bangalore’s landmark residential communities.

×